D
DCarroll
I have a resource assinged to several tasks in a project on our
project server. I noticed that the remaining work for a group of
tasks was 114.5 hours, but the end date for the task group was out
futher than I expected based on the remaining work.
I check the resource availability from the PWA screen and noticed that
on two days in one week, the resource is listed as available, so my
question is why isn't the resouce's time taken up by the project?
The resource is assigned at 100% on a M-F work week. On Thursday of
one week, it shows the resource as 8h available. I need that 8h for
that resource dedicated to the project.
project server. I noticed that the remaining work for a group of
tasks was 114.5 hours, but the end date for the task group was out
futher than I expected based on the remaining work.
I check the resource availability from the PWA screen and noticed that
on two days in one week, the resource is listed as available, so my
question is why isn't the resouce's time taken up by the project?
The resource is assigned at 100% on a M-F work week. On Thursday of
one week, it shows the resource as 8h available. I need that 8h for
that resource dedicated to the project.