D
dlg
I am working to implement Project Pro & Project Server 2003. I set up custom
enterprise resource outline code 20 as a multi-value field for skills.
Generic resources were added to the enterprise resource pool with various
skills. I also added a resource to the enterprise resource pool with a
matching skill. I set up an enterprise project where one of the generic
resources was assigned 35 tasks. I tried to do resource substitution for
this generic resource with the resource that has the matching skill. The
first 30 tasks listed were re-assigned as desired. It ignored the last 5
tasks and still kept them assigned to the generic resource. I tried to run
resource substitution again and it still ignores those tasks. I tried to do
this in another project and got the same results. Does anybody have any
ideas why this is happening?
enterprise resource outline code 20 as a multi-value field for skills.
Generic resources were added to the enterprise resource pool with various
skills. I also added a resource to the enterprise resource pool with a
matching skill. I set up an enterprise project where one of the generic
resources was assigned 35 tasks. I tried to do resource substitution for
this generic resource with the resource that has the matching skill. The
first 30 tasks listed were re-assigned as desired. It ignored the last 5
tasks and still kept them assigned to the generic resource. I tried to run
resource substitution again and it still ignores those tasks. I tried to do
this in another project and got the same results. Does anybody have any
ideas why this is happening?