Isn't there a way to allow a resource manager to change an assignment
of one of their generic resources (like "DBA" or "Tech Services") to a
"real" resource in their group in ANOTHER PMs project without having
update access to the other project?
Say the Project Manager assigns generic resource "DBA" to a task not
knowing who is available. Then I as the DBA Manager changes the "DBA"
to "John Doe" once I know who they can have.---but without update
access to the Project Manager's project.
Thanks,
Andy
of one of their generic resources (like "DBA" or "Tech Services") to a
"real" resource in their group in ANOTHER PMs project without having
update access to the other project?
Say the Project Manager assigns generic resource "DBA" to a task not
knowing who is available. Then I as the DBA Manager changes the "DBA"
to "John Doe" once I know who they can have.---but without update
access to the Project Manager's project.
Thanks,
Andy