Resource Substitution ...

B

bennido

Hi all,

I created a plan with enterprise generic resources
assigned to tasks. I also modified the Enterprise
Resource Outline Field 1 to contain the skill codes. I
then went to the Enterprise Global to update the
resources (both generic and actual) with the proper skill
codes from the lookup.

When I run the Resource Substitution wizard, it replaces
the generic resources with actual resources but it does
not match with the skill ! Please help.
 
G

Gary Chefetz [MVP]

Benny:

When you setup the outline code, did you select the checkbox to use this
code for skillset matching?

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 