A
averied
Hi,
There is this issue I need to solve.. We have a few external resources
assigned to some tasks in a project. So one of them isn't returning to our
office, so all his tasks must be assigned to a new resource. I need all the
tasks, and real hours reported by the old resurce to be assigned to the new
one.. Is there some way to do this??
Next time I'm thinking of creating resources with username external1,
external2, etc.. because everytime a new resource arrives to subsitute an old
one I have this type of problem, and I don't know what procedure I must
follow exactly..
The situation now is that when I open the project the task are assigned to a
deleted resource, as I deleted the old user from AD and Project Server
database. I added the new resource to AD and synchronized with the resource
pool.
So basically I need a solution for the actual problem, and some procedure to
follow the next time I have to change a resource and assign the tasks and
hours reported..
Thanks..
There is this issue I need to solve.. We have a few external resources
assigned to some tasks in a project. So one of them isn't returning to our
office, so all his tasks must be assigned to a new resource. I need all the
tasks, and real hours reported by the old resurce to be assigned to the new
one.. Is there some way to do this??
Next time I'm thinking of creating resources with username external1,
external2, etc.. because everytime a new resource arrives to subsitute an old
one I have this type of problem, and I don't know what procedure I must
follow exactly..
The situation now is that when I open the project the task are assigned to a
deleted resource, as I deleted the old user from AD and Project Server
database. I added the new resource to AD and synchronized with the resource
pool.
So basically I need a solution for the actual problem, and some procedure to
follow the next time I have to change a resource and assign the tasks and
hours reported..
Thanks..