S
Steve Budzynski
When uploading a project a particular resource is able to state what
percentage of work is done on any task for that particular project.
My problem is that some tasks require work to be done by other resources
before that particular person may begin their task. For example: throw away
trash would have to happen before someone can take out trash, therefore the
predecessor to take out trash is throw away trash but the resource who is
supposed to take out the trash is able to say whether or not their task is
complete before resource has stated the trash has been thrown away.
Is there anyway I can "lock out" the ability to update tasks whos
predecessors have yet to be completed? I only want my employee to be able to
update a task once the predecessor has been completed.
Please let me know if my question is not very clear. I apologize in advance
if this is an easy fix but I am very very new to MS Project!
Thank you,
percentage of work is done on any task for that particular project.
My problem is that some tasks require work to be done by other resources
before that particular person may begin their task. For example: throw away
trash would have to happen before someone can take out trash, therefore the
predecessor to take out trash is throw away trash but the resource who is
supposed to take out the trash is able to say whether or not their task is
complete before resource has stated the trash has been thrown away.
Is there anyway I can "lock out" the ability to update tasks whos
predecessors have yet to be completed? I only want my employee to be able to
update a task once the predecessor has been completed.
Please let me know if my question is not very clear. I apologize in advance
if this is an easy fix but I am very very new to MS Project!
Thank you,