Resource Tasks

  • Thread starter Scott Wagner, PMP
  • Start date
S

Scott Wagner, PMP

A resource with many tasks in various projects does not have any tasks
showing up in the Tasks page. When I check "View Resource Assignments" under
resources I also get no task information for that resource.

The resource is an "Enterprise Resource" and is listed as a Project Manager.
I have checked both the resource settings and security settings to validate
accuracy. I can find no issue with the resource.

If I republish assignments on a plan where this resource is allocated to a
task only other resources (Not this resource record) tasks show up in the
update task list. I have been working with project server since Project
Central (2000) and I have never seen this.

Any help or recommendations would be appreciated.
 
D

Dale Howard [MVP]

Scott --

Has this resource EVER been able to see task assignments in PWA? If not, is
there a possibility that the resource's default Booking value is set to
Proposed rather than Committed in the Enterprise Resource Pool? Let us know
and we'll try to help.
 