A resource with many tasks in various projects does not have any tasks
showing up in the Tasks page. When I check "View Resource Assignments" under
resources I also get no task information for that resource.
The resource is an "Enterprise Resource" and is listed as a Project Manager.
I have checked both the resource settings and security settings to validate
accuracy. I can find no issue with the resource.
If I republish assignments on a plan where this resource is allocated to a
task only other resources (Not this resource record) tasks show up in the
update task list. I have been working with project server since Project
Central (2000) and I have never seen this.
Any help or recommendations would be appreciated.
showing up in the Tasks page. When I check "View Resource Assignments" under
resources I also get no task information for that resource.
The resource is an "Enterprise Resource" and is listed as a Project Manager.
I have checked both the resource settings and security settings to validate
accuracy. I can find no issue with the resource.
If I republish assignments on a plan where this resource is allocated to a
task only other resources (Not this resource record) tasks show up in the
update task list. I have been working with project server since Project
Central (2000) and I have never seen this.