resource tasks

X

xsd

i need to print a list with tasks of next month, group by people. if i go to
resource usage view, i have a list of tasks, but i don't know project name of
each task (so, i've a lot of "design" or "maintenance" tasks)..

can i print this king of lists?

(sorry my poor english...)
 
J

JulieS

Hi xsd,

In the Resource Usage view, try inserting the project field if you are
working with a consolidated project.

If you wish to see the name of the summary task for each assignment, try
inserting the Task Summary Name field.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
X

xsd

i'm new in project... not know about consolidated project but it seems it can
be the solution... tkx a lot!!!
 