X
Xia Mei
Hi,
I need help on these three things:
1. By default, if a user does not specify a resource type to be material or
cost, microsoft project will set the resource type as work.
I need to change the default value from work to material.
2. By default, if in Options -> Schedule -> work is entered in -> is set
into months then Microsoft Project will display 8 mons. I need to remove the
unit, so it will only be displayed as 8.
3. By default, there are 3 task types in Microsoft Project: Fixed duration,
Fixed units and Fixed work. I need to remove or hide the Fixed units and
Fixed work so that in the drop down box there is only Fixed duration.
Can anyone please help me on how to achieve those three things above? Either
by setting or coding.
Thank you
I need help on these three things:
1. By default, if a user does not specify a resource type to be material or
cost, microsoft project will set the resource type as work.
I need to change the default value from work to material.
2. By default, if in Options -> Schedule -> work is entered in -> is set
into months then Microsoft Project will display 8 mons. I need to remove the
unit, so it will only be displayed as 8.
3. By default, there are 3 task types in Microsoft Project: Fixed duration,
Fixed units and Fixed work. I need to remove or hide the Fixed units and
Fixed work so that in the drop down box there is only Fixed duration.
Can anyone please help me on how to achieve those three things above? Either
by setting or coding.
Thank you