Hi

We are using Project Server 2003.

Project manager had assigned a task to a resource. But, the resources was
unable to see the task in his timesheet.

However, with administrator login, I am able to see the task in his
timesheet.

Any ideas on this would be appreciated.

Thank you
Shiva Chaitanya.
 