Resource Unit changes

J

James from Sage

I'm using Project Server 2003. When we allocate a resource unit percentage -
it looks like the % displayed ends up being the maximum allocation based on
actuals if higher than what was originally allocated.

A) How exactly is this new % allocation calculated?

B) Does the new % allocation ever affect the duration?

Thanks,

- James
 
J

Jan De Messemaeker

Hi,
Calculations only happen oin Project Professional so I suppose that's what
you refer to.
1. As you have seen the maximum at any time
2. Not as lo,ng as the task has never been 100% complete; Project goes on
calculating based on the original (fortunately!) However when you make the
task 100% complete, the afterwards add remaining work, this remaining work
will be planned with the "new" units.
A nuisance, I know, but I cna't help.

HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top