Yoav
I Defined a task, type of Fixed Units, and duration of 10 days.
I assigned a resource with 20% units. (work is 16 hours).
On a specific day I report via the 'resource usage' report 2 hours of actual
work where the planned in 1.6 hours. The units to the task changes to 25%.
Why is that?
Now I changed the allocation back to 20%, and increased the remaining work
from 14 hours to 20 hours. The units changed back again to 25%. Why are the
unit changes where the task is fixed units? is this a bug? Is there a
wordaround?
Thanks!
I assigned a resource with 20% units. (work is 16 hours).
On a specific day I report via the 'resource usage' report 2 hours of actual
work where the planned in 1.6 hours. The units to the task changes to 25%.
Why is that?
Now I changed the allocation back to 20%, and increased the remaining work
from 14 hours to 20 hours. The units changed back again to 25%. Why are the
unit changes where the task is fixed units? is this a bug? Is there a
wordaround?
Thanks!