Resource Unit Percentage

J

Jackie

I've changed my resource unit to 60% for my staff, but
when I have to change the work days it doesn't calculate
with the new work days.

How can I configure to calculate automatically?

Thank you,

Jackied
 
J

Jan De Messemaeker

Hi Jackie,

Project calculates with what it finds in the working time calendar.
It does not automatically adapt assignment units to max. units
HTH
 