Hello,
I have a part time resource who worked 10 hours per week on a project. Her
calendar was changed to reflect working 2 hours per day and her resource
units set to 100%. Recently, it was approved for her to increase to 20 hours
per week (effective 09/01/08). In the Resource Availability section I
increased her resource units to 200% for 09/01/08 - 12/31/09. Based on the
resource usage sheet, or some days past 09/01/08, she is now scheduled to
work 4 hours. For other days, however, she is still scheduled to work only 2.
Can you help me understand why this would be, and what I will need to do to
ensure that she is not under-utilized? I have tried leveling but it has not
helped.
Thank you for any insight you can provide
I have a part time resource who worked 10 hours per week on a project. Her
calendar was changed to reflect working 2 hours per day and her resource
units set to 100%. Recently, it was approved for her to increase to 20 hours
per week (effective 09/01/08). In the Resource Availability section I
increased her resource units to 200% for 09/01/08 - 12/31/09. Based on the
resource usage sheet, or some days past 09/01/08, she is now scheduled to
work 4 hours. For other days, however, she is still scheduled to work only 2.
Can you help me understand why this would be, and what I will need to do to
ensure that she is not under-utilized? I have tried leveling but it has not
helped.
Thank you for any insight you can provide