I have an ePM user asking why if he enters a project task in PWA does
it not check the resource max units allocation the same way as when he
enters a task in Project Professional.
For example:
You have a project where resource A is 50% allocated. When you create
a task in Project Professional for this resource, the resource
allocation is set to 50%.
Create a task under the same project in PWA, submit and approve the
task.
Open project professional and view the task information for the task
entered in PWA, why is the resource allocation set to 100% instead of
50% set for this resource?
Environment -
MICROSOFT OFFICE PROJECT - SERVER
=====================================
Product Version: Project Server 2007
Service Pack: Feb CU
Project Server Application Server
OS/SERVICE PACK: Windows Server 2003 R2 Enterprise SP2 32-bit
INSTALLED APPLICATIONS:
Project Server 2007
Moss 2007 binaries
Project Server DB Server
OS/SERVICE PACK: Windows Server 2003 R2 Enterprise SP2 32-bit
INSTALLED APPLICATIONS: SQL Server 2005 SP2
Project Professional Client
Microsoft Office Project 2007 (12.0.6423.1000) SP2 MSO
(12.0.6425.1000)
Does anyone have any insight on this?
Thanks
Mollie
I have an ePM user asking why if he enters a project task in PWA does
it not check the resource max units allocation the same way as when he
enters a task in Project Professional.
For example:
You have a project where resource A is 50% allocated. When you create
a task in Project Professional for this resource, the resource
allocation is set to 50%.
Create a task under the same project in PWA, submit and approve the
task.
Open project professional and view the task information for the task
entered in PWA, why is the resource allocation set to 100% instead of
50% set for this resource?
Environment -
MICROSOFT OFFICE PROJECT - SERVER
=====================================
Product Version: Project Server 2007
Service Pack: Feb CU
Project Server Application Server
OS/SERVICE PACK: Windows Server 2003 R2 Enterprise SP2 32-bit
INSTALLED APPLICATIONS:
Project Server 2007
Moss 2007 binaries
Project Server DB Server
OS/SERVICE PACK: Windows Server 2003 R2 Enterprise SP2 32-bit
INSTALLED APPLICATIONS: SQL Server 2005 SP2
Project Professional Client
Microsoft Office Project 2007 (12.0.6423.1000) SP2 MSO
(12.0.6425.1000)
Does anyone have any insight on this?
Thanks
Mollie