J
Jack
I had always thought that on a fixed duration task (like say, a 2 hour
meeting), the resource units should all be 100% since every resource is in
the meeting 100% of the time for the whole 2 hours. Would there be any
circumstances when the resource units would be less than 100%?
meeting), the resource units should all be 100% since every resource is in
the meeting 100% of the time for the whole 2 hours. Would there be any
circumstances when the resource units would be less than 100%?