Hi
I have a resource with 200% units in the resource pool. I understand that
this means that the resource will not be considered over allocated if he was
assigned to a task with more than 100% unit but less than 200%. is that true?
When I assign the previous resource to a task and give the assignment 150%
unit, it shows the resource in a red as he is over allocated. But why if he
has 200% unit defined in the resource pool?
Regards
Mohammad
I have a resource with 200% units in the resource pool. I understand that
this means that the resource will not be considered over allocated if he was
assigned to a task with more than 100% unit but less than 200%. is that true?
When I assign the previous resource to a task and give the assignment 150%
unit, it shows the resource in a red as he is over allocated. But why if he
has 200% unit defined in the resource pool?