J
John K
I want to be able to have a resource, say 'electrician', with 5 available for
the day shift and 2 available for the night shift. This would allow e to
just assign the 'electrician' resource and have project level based on unit
availability.
If I setup 'electrician Day' and 'electrician Night', then I need to
carefully select which to use and if the schedule shifts it is a nightmare.
Any thought on how to do this?
Thank-you!
the day shift and 2 available for the night shift. This would allow e to
just assign the 'electrician' resource and have project level based on unit
availability.
If I setup 'electrician Day' and 'electrician Night', then I need to
carefully select which to use and if the schedule shifts it is a nightmare.
Any thought on how to do this?
Thank-you!