Resource units

J

jlbreyer

When resource names are displayed next to the task bar in
Gantt Chart view, any units other than 100% is displayed
in brackets after the name. Is there a way to display the
name alone? That is, without displaying the units?
thanks
jlb
 
G

Gérard Ducouret

Hello jlb,

In the Resource Sheet, you copy the Resource Name in the Resource Initials
field.
Then, in the Gantt Chart for ex., you display the Resource Initials instead
of the resource name :

Format / Bar Styles / Text... / Right...

Gérard Ducouret
 
J

jlb

Thanks. That makes sense as a work around. My first
reaction is "DUH! Why didn't I think of that?"
jlb
 