HI,
I am new to PS and my question is this:
My PM has assigned a resource to every task. When the plan was put into
Project Server, emails were sent to the resources and they are assigned those
tasks. Which means they can update the %complete fields and the actual
dates. The status has been collected this way for 5 months. The PM now wants
the resource managers to be able to update the %complete and dates fields for
All the resources that the manager manages. Right now we allow the resources
to status their tasks each month. The PM wants to change this step and have
the resources report the status to a resource manager, who in turn would
enter the data into the Project via Project Server. Only the PM and scheduler
have access to the Project outside of Project Server. All others access the
project via Project Server.
How can I do this, I have not been able to get the resource manager
permission to update tasks.