P
ProModeler
I am creating a new combination view. It has the Gantt Chart in the top
pane, and the Resource Usage in the bottom pane. Currently, when I click on
a task in the Gantt Chart, the Resource Usage table shows a list of the
resources assigned to that task. However, under each resource name is the
entire list of tasks for that resource.
I would like only the tasks I have selected in the Gantt Chart to be listed
under each resource in the Resource Usage table. For example, if Task1 has
Resource1 assigned, and I select Task1, I want only Task1 to appear in the
task list under Resource1 in the Resource Usage table, even if Resource1 is
also assigned to Task2.
Is there a filter or group I could use to acheive this?
Thanks!
pane, and the Resource Usage in the bottom pane. Currently, when I click on
a task in the Gantt Chart, the Resource Usage table shows a list of the
resources assigned to that task. However, under each resource name is the
entire list of tasks for that resource.
I would like only the tasks I have selected in the Gantt Chart to be listed
under each resource in the Resource Usage table. For example, if Task1 has
Resource1 assigned, and I select Task1, I want only Task1 to appear in the
task list under Resource1 in the Resource Usage table, even if Resource1 is
also assigned to Task2.
Is there a filter or group I could use to acheive this?
Thanks!