I have a resource on a project. The resource is allocated at 100%. On the
Gantt view, it shows that she is allocated on task 1 from 2/1/2007 through
2/21/2007 at 10% along with 4 other resources at varying units. The total
hours for the task is 31 hours. It also shows that she is allocated on task 2
from 2/1/2007 through 2/21/2007 at 10% along with 4 other resources at
varying units. The total hours for this task is 30 hours.
However, when I go to the resource usage view, it shows that my resource has
no hours assigned in the month of February. I've doubled the percentage of
units for this resource on the task and it still doesn't update the dates in
February for the task. I have other resources on the plan that have usage at
a level of .08 spread out over a time period. Why won't this task behave the
same?
Gantt view, it shows that she is allocated on task 1 from 2/1/2007 through
2/21/2007 at 10% along with 4 other resources at varying units. The total
hours for the task is 31 hours. It also shows that she is allocated on task 2
from 2/1/2007 through 2/21/2007 at 10% along with 4 other resources at
varying units. The total hours for this task is 30 hours.
However, when I go to the resource usage view, it shows that my resource has
no hours assigned in the month of February. I've doubled the percentage of
units for this resource on the task and it still doesn't update the dates in
February for the task. I have other resources on the plan that have usage at
a level of .08 spread out over a time period. Why won't this task behave the
same?