Resource Usage Filter for in progress tasks?

D

davegb

I would like to create a filter on the resource usage view to see only
tasks that have work scheduled in a given time period. I.e., Resource
Usage showing tasks with work scheduled between 6/14 & 6/25. Does
anyone know how to create such a filter, or does one exist in Project?
Thanks for the help.

Dave Bellamy
 
J

JackD

Go to the resource usage view.
From the project menu select "filtered for..." then "more filters"
Look for the "date range..." filter.

If that doesn't work the way you want you can edit it.
Look at some of the other pre-defined filters for ideas and how to write the
correct filter criteria.

-Jack
 
D

davegb

Thanks, Jack, that's it.
Dave

JackD said:
Go to the resource usage view.
From the project menu select "filtered for..." then "more filters"
Look for the "date range..." filter.

If that doesn't work the way you want you can edit it.
Look at some of the other pre-defined filters for ideas and how to write the
correct filter criteria.

-Jack
 