P
Patc
I am working with a resource pool
Individual projects are established using this
Attempt to utilise resources < 100% for a particular project
Aim: to determine resource usage per individual as well as have line of site
easily for when resources become available
1)Open the project resource usage icon and select a resource
2)Some task sets for that resource appear more than one 3 times for example
(Meeting ,Compile stress test environment,Adapt Data Loading scripts with
the associated time is there x3) thus the total time allocation for the day
is calculated three times , giving a huge overutilisation ( not
intentionally!)
Please can you help
Individual projects are established using this
Attempt to utilise resources < 100% for a particular project
Aim: to determine resource usage per individual as well as have line of site
easily for when resources become available
1)Open the project resource usage icon and select a resource
2)Some task sets for that resource appear more than one 3 times for example
(Meeting ,Compile stress test environment,Adapt Data Loading scripts with
the associated time is there x3) thus the total time allocation for the day
is calculated three times , giving a huge overutilisation ( not
intentionally!)
Please can you help