S
Simha
Hi
I want to generate a Resource Usage for a particular day, to know who did
what for the day. (Kind of TimeSheet for the day)
I did try with Who-does-what-when under Reports->Assignemnts,
but that gives me for the entire project. My report should look something
similiar to this.
Resource Report as on : 03/01/06
------------------------------------------------------------------
Tasks Resource-A Resource-b
------------------------------------------------------------------
Coding 8h 4h
Testing 0h 4h
------------------------------------------------------------------
I have even tried with macros using (TimeScaleData object) what I can
extract from this is the total time for a Resource, but not against which
Task.
Any help on this will save my job.
Thanks in advance
I want to generate a Resource Usage for a particular day, to know who did
what for the day. (Kind of TimeSheet for the day)
I did try with Who-does-what-when under Reports->Assignemnts,
but that gives me for the entire project. My report should look something
similiar to this.
Resource Report as on : 03/01/06
------------------------------------------------------------------
Tasks Resource-A Resource-b
------------------------------------------------------------------
Coding 8h 4h
Testing 0h 4h
------------------------------------------------------------------
I have even tried with macros using (TimeScaleData object) what I can
extract from this is the total time for a Resource, but not against which
Task.
Any help on this will save my job.
Thanks in advance