Resource Usage Report

B

bill w.

I have recurring meetings throughout the year; twice a week for 1 hour each.
But when I run the Resource Usage Report, it shows I am using 40 per week on
the meeting. How do I correct the report so it shows just 2 hours per week?
 
B

bill w.

Never mind... I had the resource on the summary task instead of the
individual subtasks.
 
R

Rod Gill

Hi,

The recurring meeting should be 1h long twice a week. Expand the recurring
task to see the individual meetings. If there aren't 2x1h meetings, delete
them all and re-create the recurring task.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top