R
Roland
In the 2007 resource usage view I am dealing with a quandry. Why would a
summary hours not equal all the projects/tasks hour under it? I have the
"Load Summary Resoure" option checked. Summary has 900 hours for 1 week
whereas the included projects/tasks only show 250. Hopefully a simple answer.
Thanks!!
summary hours not equal all the projects/tasks hour under it? I have the
"Load Summary Resoure" option checked. Summary has 900 hours for 1 week
whereas the included projects/tasks only show 250. Hopefully a simple answer.
Thanks!!