I am trying to get the Resource Usage view (Entry table) to display Days in
all the cells. I have clicked Options > Schedule tab, and set "Work is
entered in" as "Days". This does change all the values for the task rows
under each resource to display in days, but the total row against each
resource name itself still shows hours. I have also tried changing the
Enterprise Global file, but this did not have any effect. I have read a
similar thread where it was recommended to specify the Options value in each
individual project (rather than the Enterprise Global file), which I believe
I have done (open the project, and click Options, etc).

Can someone please shed light on this ?
 
K

Kurt Verhaegen

Hi,

In an enterprise environment I' ve seen that setting the work unit in the
schedule tab under Tools\Options does not control the summary line at the
resource usage view.
This is controlled by the EGT, so if you change it in the EGT and set it as
default.
Restart winproj and check it again it should reflect the time unit as
specified in the EGT.

Grtz, Kurt
Exerti
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top