We are using Project Server 2007 / Project Professional 2007.
I am trying to get the Resource Usage view (Entry table) to display Days in
all the cells. I have clicked Options > Schedule tab, and set "Work is
entered in" as "Days". This does change all the values for the task rows
under each resource to display in days, but the total row against each
resource name itself still shows hours. I have also tried changing the
Enterprise Global file, but this did not have any effect. I have read a
similar thread where it was recommended to specify the Options value in each
individual project (rather than the Enterprise Global file), which I believe
I have done (open the project, and click Options, etc).
Can someone please shed light on this ?
I am trying to get the Resource Usage view (Entry table) to display Days in
all the cells. I have clicked Options > Schedule tab, and set "Work is
entered in" as "Days". This does change all the values for the task rows
under each resource to display in days, but the total row against each
resource name itself still shows hours. I have also tried changing the
Enterprise Global file, but this did not have any effect. I have read a
similar thread where it was recommended to specify the Options value in each
individual project (rather than the Enterprise Global file), which I believe
I have done (open the project, and click Options, etc).
Can someone please shed light on this ?