Resource Usage view & Figures

D

Daniel

Hello.-

I'm a bit confused about how to interpret the Reource usage view when I'm
connecto to Project Server, my problem/situation is this:

When you are connected to project server 2003 and open the Resource ussage
view you can see the figures for all assigments for all resources that are
part of yor project plan, tghis implies by example: If I'm looking my own
woork and completed work figures in this view I see not only the total
numbers for this project, but also to all others projects where I'm a
resource, so the roll-ou figures include the Work a Completed Work for the
actula open project (where I'm activating the Reource Usage View) and the
other ones publisehd in project whre I'm a resource with assigned work.

Have some one an idea about how can I filter to see only the figures for the
currently open project?

I will appreciate any help.

PD: If you delete the rollout figures for the assigments in other projects
(not actually open), sometimes the grand total figure (at resource level)
actualize its results, but some times not, even if you refresh the view.
 