Resource Usage View grouped by Projects

S

Steve Scott

I need to to be able to group my assignments in my Resource Pool by Resource
then Project then the assignments - is this possible?
 
J

JulieS

Hi Steve,

In the Resource Usage view create the following group:

Group By
Field: Name
Field Type: Resource
Order: Ascending

Then By
Field: Project
Field Type: Assignment
Order Ascending

To be able to group by assignment, you'll need to check (enable) the
option "Group assignments, not resources."

I hope this helps. Let us know how you get along.

Julie