Resource Usage View: hours for non-working day

A

AG

Hi

In my resource usage view work hours are shown for a
resource task for a Sunday when the timescale is set to a
per day view. The particular resource base calendar is
set to the standard calendar and the date (Sunday) shows
as a non-working day.
How is it possible that work hours are shown for a non-
working day?

Regards
AG
 
J

Jan De Messemaeker

Hi,

Someone may have entered actual Work for this day.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
G

Gérard DUCOURET

Hi,
In the resource calendar, you set the sunday as a working day, and you will be abble to display work
hours on that sunday.

Gérard Ducouret
 