R
Ralf
Dear MS Project Experts,
The "Resource Usage" view displays a list of resources and the tasks
assigned to them. But for every task I'd also like to see the other
resources assigned to the same task. The "insert column" dialog doesn't
have a "Resources" option. So how can I add a resources column to the view?
Like this:
Resource Name Resources
- Harry
task 1 Harry
task 2 Harry; Fred
- Fred
task 2 Harry; Fred
I'd appreciate any comment.
Thank you!
Ralf.
(MS Project Prof. 2002)
The "Resource Usage" view displays a list of resources and the tasks
assigned to them. But for every task I'd also like to see the other
resources assigned to the same task. The "insert column" dialog doesn't
have a "Resources" option. So how can I add a resources column to the view?
Like this:
Resource Name Resources
- Harry
task 1 Harry
task 2 Harry; Fred
- Fred
task 2 Harry; Fred
I'd appreciate any comment.
Thank you!
Ralf.
(MS Project Prof. 2002)