Andy Wiltz
In the resource usage view, the task work is listed in days and the rollup
(the line with the resource name) is listed in hours. I checked the
settings for the workplan, and it is supposed to be showing in days. Also,
I checked the Enterprise Global, and work is supposed to be reported in days
as well. No matter what I do, I cannot get the rollup line to change from
hours to days. The task work will change between the two though. This only
happens when the project is posted on Project Server. It doesn't happen if
it is a local workplan on my hard drive.
Any ideas?
(the line with the resource name) is listed in hours. I checked the
settings for the workplan, and it is supposed to be showing in days. Also,
I checked the Enterprise Global, and work is supposed to be reported in days
as well. No matter what I do, I cannot get the rollup line to change from
hours to days. The task work will change between the two though. This only
happens when the project is posted on Project Server. It doesn't happen if
it is a local workplan on my hard drive.
Any ideas?