resource usage view shows only one resource

B

Ben

Hi,

When I select the Resource Usage View, only one resource appears in the view
even if there are around 20 assigned resources. Earlier this week, the view
was correct and all resources were shown.

The only thing I did lately is to create a new version type. So now I have
the ability to save the project in ".published" version as well as a ".B1"
version. In the ".B1" version I can see all resources in the Resource Usage
View but not with ".published" version.

What could be my problem?

Thanks
 
D

Dale Howard [MVP]

Ben --

In your .Published version, do you have a filter applied in the Resource
Usage view? That might explain why you see only one resource. Let us know.
 
B

Ben

Hi Dale,

Thanks for your answer. The filter was set to "All resources". However, I
re-apply it and all resources re-appear. Now, everything is alright.

Thanks again.
 