J
John L.
Hello
I have multiple projects that I have created a pooled resource and one
master project. I have linked all of the projects together, but when I
delete a particular project, the Gantt Chart reflects it correctly, but the
Resource Usage view still shows the resources and tasks from the project I
just deleted. I also changed the 'shared resources' to 'use own resources'
for the project I removed from the master project.
Please let me know how to 'refresh' with the current linked projects only in
the Resource Usage view.
thank you
john
I have multiple projects that I have created a pooled resource and one
master project. I have linked all of the projects together, but when I
delete a particular project, the Gantt Chart reflects it correctly, but the
Resource Usage view still shows the resources and tasks from the project I
just deleted. I also changed the 'shared resources' to 'use own resources'
for the project I removed from the master project.
Please let me know how to 'refresh' with the current linked projects only in
the Resource Usage view.
thank you
john