F
Frederick
Good day,
Using MSP2003 Pro, SP2-A. In the view "resource usage"
->for the resource, i.e. the "summary task", the work, actual & rem are
displayed in "hours" (hrs)
->for the tasks in the same view, for the "detailed tasks", the work, actual
& rem are displayed in "days" (d).
I would like both to be displayed in days; I have looked about a hundred
times at the Tools, Option panel, both options are set to "entered and
displayed in days", the same result as above persists.
Please advise if you know how to change the display config for this, thanks!
Using MSP2003 Pro, SP2-A. In the view "resource usage"
->for the resource, i.e. the "summary task", the work, actual & rem are
displayed in "hours" (hrs)
->for the tasks in the same view, for the "detailed tasks", the work, actual
& rem are displayed in "days" (d).
I would like both to be displayed in days; I have looked about a hundred
times at the Tools, Option panel, both options are set to "entered and
displayed in days", the same result as above persists.
Please advise if you know how to change the display config for this, thanks!