Hmmmmmm! You're right about the assignments, and I can't argue with the most of your statements. However, the use of the in-built Priority field could conflict with automatic resource levelling, if for example, levelling priority was defined differently from "priority" based on an assessmentof some other value like its importance. I thus believe that the Priority field should only be used to direct automatic levelling.
It does depend on exactly what Carrie is after. I assumed she wanted to view the Resource Usage view and filter there. There's no reason why she can't enter priorities against the assignments - presumably, if there was more than one assignment on a task, the other resource assignments would be the similarly marked. If she's only interested in the highest level of importance, then a simple Flag field could suffice.
Mike Glen
Project MVP
Seehttp://tinyurl.com/2xbhcfor my free Project Tutorials
On Jan 6, 3:34 pm, "Mike Glen" <mcglenAThotmail.com> wrote:
> Hi Carrie,
>
> Welcome to this Microsoft Project newsgroup
>
> Firstly a reminder that the Priority field is used by Project solely when using its resource levelling feature - nothing else. In Resource Usage view, Insert a Text field and enter the various priorities you want. Then you can Autofilter the column to show only the priority you want.
>
> FAQs, companion products and other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm
>
> Hope this helps - please let us know how you get on
>
> Mike Glen
> MS Project MVP
> Seehttp://tinyurl.com/2xbhcformy free Project Tutorials
>
> I need to filter and sort a resource usage view based on the priority of
> tasks. Is this possible? we have a development plan with three different
> priorities and I need to filter on high level priority tasks only. I also
> need to be able to see timephased data for the specific resource so I can
> reallocate time to a lower priority task. thanks.
>
Mike - Just want to share my thoughts about your answer.
Carrie's question was about "... we have a development plan with three
different priorities and I need to filter on high level priority tasks
only" indicating the priority is more at the task rather than at the
assignment level.
As per your anwser, we can insert a custom field in the Resource Usage
view to store the priority of the task, but remember, this new user
defined column will store the priority at assignment level and not at
the task level.
This will introduce few rework later
1) If a task has multiple resources and its priority changes, we need
to make multiple changes in Resource usage / Task usage; as the same
task is assigned multiple resources
2) This custom field cannot be used for resource leveling, which is a
key feature of scheduling.
So, I suggest we insert "Priority" field in task sheet (in any Gantt
chart view), so that the above problems can be avoided.
Please let me know if my thoughts are right,
- Sai, PMP, PMI-SP, MCT, MCTS
http://saipower.wordpress.com
__________ Information from ESET Smart Security, version of virus signature database 4747 (20100106) __________
The message was checked by ESET Smart Security.
http://www.eset.com