R
Reuben Hecquet
Using PS 2003 with PP 2003 both with SP1 applied.
If a user opens a plan in PP and looks at the resource usage view they
see the correct information for acutal or remaining for a resource in
relation to the plan opened. The view also allows you to see the other
plans that the resource is assigned to. The actual and remaining
information displayed here for these other plans is often wrong
(usually 0's). If you look at the same view within PWA for a resource
all is correct, you see the correct information for all plans that the
resource is assigned. The information is always correct in PP for the
plan opened only not other plans.
Any suggestions ?
Much appreciated.
If a user opens a plan in PP and looks at the resource usage view they
see the correct information for acutal or remaining for a resource in
relation to the plan opened. The view also allows you to see the other
plans that the resource is assigned to. The actual and remaining
information displayed here for these other plans is often wrong
(usually 0's). If you look at the same view within PWA for a resource
all is correct, you see the correct information for all plans that the
resource is assigned. The information is always correct in PP for the
plan opened only not other plans.
Any suggestions ?
Much appreciated.