Resource Usage View

J

Jonathan Vardy

Hi,

I'm having a little issue with the Resource Usage View in Project Pro 2003.
If as a resource manager I open project A, I see the resource assignments of
only project A. Once I open project B, I can see resoruce assignments of both
projects A and B.

I have the same issue when I only open project A and try to look at the
resource graph. Without project B open it will only show me the resource
usage of project A and sometimes that means an incorrect availability graph.

What I would like is that once I've opened project A, I can see the resource
assignments and usage of all the projects.

Have I missed a security permission somewhere? Any help would be appreciated.

Thanks, Jonathan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top