Resource Usage View

G

Gsne

I would like to include summary tasks in my Resource Usage Views (to use for
filters
and Reports)

Under Tools, Options, View,
The Show Summary Tasks option is greyed out.

Is there any way of making this an option.

Thanks,

Gsne
 
J

JulieS

Hello Gsne,

Sorry, not directly. The task names you see when looking at the
Resource Usage view are really assignments (pairing of resource and
task) not tasks, therefore summary tasks won't appear. You can,
however insert the column Task Summary Name to the table (left side)
to show the name of the assignment's summary.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 