K
Kirsten
When I view my Resource Usage I have the Resource Name and Work. I always
pull in an extra column "Task Summary" so I can see which task they are
working on in the correct module. The task summary is pulling in the word
requirements instead of the MP900 Front End System. Does anyone know how I
can get a column that pulls in the level 2 information?
- Phase 1
- MP900 Front-End System
-Requirements
pull in an extra column "Task Summary" so I can see which task they are
working on in the correct module. The task summary is pulling in the word
requirements instead of the MP900 Front End System. Does anyone know how I
can get a column that pulls in the level 2 information?
- Phase 1
- MP900 Front-End System
-Requirements