M
Mark2
I have assigned resources work at all task levels, as appropriate, making
sure that I have not double counted their effort. I pull up the Resource
Usage View, and look at work and overallocation "buckets", I have resources
that are shown to be overallocated but the work detail does not support the
overallocation. In investigating the problem, I found that the cases where I
assigned resources to a rollup task no work is being shown, and the task
itself is not showing up on the list. I have looked a variety of other
reports and views, and the resource allocation of work for the rollup tasks
does show up in them ... this a "design feature", defect, or is there a
configuration setting that I am unaware of in the application?
sure that I have not double counted their effort. I pull up the Resource
Usage View, and look at work and overallocation "buckets", I have resources
that are shown to be overallocated but the work detail does not support the
overallocation. In investigating the problem, I found that the cases where I
assigned resources to a rollup task no work is being shown, and the task
itself is not showing up on the list. I have looked a variety of other
reports and views, and the resource allocation of work for the rollup tasks
does show up in them ... this a "design feature", defect, or is there a
configuration setting that I am unaware of in the application?