G
Gsne
Using MS Project 2003 Enterprise -
Set-up Work to be viewed in Days
However, in resource Usage view Summary for resource is still showing as hrs.
Individual times against tasks showing as days.
Any ideas why summary is showing different format?
Thanks,
Set-up Work to be viewed in Days
However, in resource Usage view Summary for resource is still showing as hrs.
Individual times against tasks showing as days.
Any ideas why summary is showing different format?
Thanks,