resource usage

L

lk50

Hi there,

Is it possible to display remaining work in the right hand Pane? I ca
display it in the left hand pane (the table section) but can't seem t
find in the right hand pane (the timephased area).

eg. I want total remaining work for each resources for each month

Many thanks
 
A

Andrew Lavinsky

Nope. Remaining work is not a timephased field I believe.

That being said, if you're updating projects correctly, remaining work should
be 0 in the past, and equal to Work in the future. So the only month you
might have an issue is the current month, and that would already display
the Actual Work and Work - which is easy enough to compare.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
S

Sai

Hi there,

Is it possible to display remaining work in the right hand Pane? I can
display it in the left hand pane (the table section)  but can't seem to
find in the right hand pane (the timephased area).

eg. I want total remaining work for each resources for each month

Many thanks.

--
lk50
------------------------------------------------------------------------
lk50's Profile:http://forums.techarena.in/members/87282.htm
View this thread:http://forums.techarena.in/microsoft-project/1292777.htm

http://forums.techarena.in

Try this option. Right click the timephased area, and select "Actual
work". If the "work" and "actual work" are unequal, it indicates there
is some remaining work for that resource.

- Sai, PMP, PMI-SP, MCT, MCTS
http://saipowe.wordpress.com
 