Dale:
Sorry for the delayed response. Since we have a new user community
that
are
not setting resource units correctly across all projects wouldn't that
skew
utilization?
:
NYC --
Why would that skew utilization?
Dale:
Unfortunately, we have a situation where most of the pm's in the
organization are new, and basing off of work and resource
availability
will
skew utilization.
Would it be possbile to base it off of a fixed # of hrs (e.g.,
50hrs/week
or
200hrs/mo). If so, what would the syntax of the calc look like
using
Portfolio Analyzer. Thanks in advance.
:
Dots --
You are more than welcome, my friend!
Thanks Dale. As always - very helpful!
D
:
Dots --
Your first problem is that there is no default Weeks time
dimension
in
the
Portfolio Analyzer. To use the Weeks time dimension, you would
either
need
to extend the OLAP cube yourself through customization, or
purchase
a
software product that will do this for you automatically.
Once you get past this issue, then you can create a Portfolio
Analyzer
view
to display the data you wish to see. Here's how to set up the
View:
1. Add the Resources dimension to the Row Fields drop area
2. Add the Weeks dimension to the Column Fields drop area
3. Click the Calculated Total button on the PivotTable toolbar
and
create a
custom calculation called Percent Util. using the following
formula:
[Measures].[Work]/[Measures].[Availability]
4. Right-click the Percent Util. column header and select
Commands
and
Options from the shortcut menu
5. Select the Format tab, enter "0%" (without the quotes) in
the
Number
field to display percentage number formatting, and then close
the
dialog
6. Add this custom view to at least one Category
7. Click the Save Changes button
When a user applies this View, he/she will be able to click the
pick
list
button on the Weeks dimension and then select the Weeks he/she
wishes
to
see. Hope this helps.
Hi,
I want to be able to generate a report (data and graphics)
that
shows
total
resource utilization across all projects for x time frame.
I've
been
trying
to do this with portfolio analyzer but I am not quite getting
what I
want.
Is this something that has to be queried from the SQL end?
Anyone
have
the
query?
Here is what I want - A graph of all utilized resources only
showing
names,
% utilized by week, over a given period. Then being able to
scale
down
to
what project(s) that person may be on for a particular
timeframe.
Is this available?
Thanks,
D.