Can I make the Resource graph or Resource Usage graph available in PWA?

Meena.
 
S

Samer Beano

NewsGroup,

I can view the Resource graph as well as resource usage graph by clicking
the Resource tab from PWA.
I know that these views are defaults views when you intsall Project Server!!
 
M

Mark Everett | PMP

Meena -

In PWA, navigate to the Resource Center. Select one or more (up to 30)
resources and click on the "Availability" link. This will give you 4
availability views to choose from, with a grid below the graph that
shows you the data being used to construct the graph.

Hope this helps,

Mark Everett