resource view on gannt chart

S

Sim

Is there a way of adding resources so they are displayed on the gantt chart
view on PWA without adding them to the enterprise resource pool. Any help
will be greatfully recieved.
 
D

Dale Howard [MVP]

Sim --

You could add the resources as local resources in the project. Here's how:

1. Open the project in question
2. Click View - Resource Sheet
3. Type the name of each local resource
4. Double-click the name of the first local resource
5. Set the Workgroup value to None
6. Click OK
7. Repeat steps #4-6 for each local resource
8. Save your project

After doing this, assign your local resources to one or more tasks and then
click Collaborate - Publish - All Information. The names of the local
resources will appear in any detailed Project view in PWA that displays
resource information. Hope this helps.
 
S

Sim

looks to have worked thanks alot!

Dale Howard said:
Sim --

You could add the resources as local resources in the project. Here's how:

1. Open the project in question
2. Click View - Resource Sheet
3. Type the name of each local resource
4. Double-click the name of the first local resource
5. Set the Workgroup value to None
6. Click OK
7. Repeat steps #4-6 for each local resource
8. Save your project

After doing this, assign your local resources to one or more tasks and then
click Collaborate - Publish - All Information. The names of the local
resources will appear in any detailed Project view in PWA that displays
resource information. Hope this helps.
 