bernward
I have three fulltime resource. (100%)
On resource has one week off in his resourcecalendar. (exception days
8.-12.3.)
A have a task fixed work task with 360h work. When I assign the
resouce with the exception days at the end, all get 120h to work. But
when I assign the ressouce with the exeption day first then I get a
different result:
111,72 h for the first resource (with the exception days)
111,72 h for the second resource and
136,72 h.for the last resouce.
Why get I the different result?