Hey,
We have a few support tasks where we have been setting Duration to 0
and then assigning everyone on the team to the task in order to report
against it each week.
Over time, they have reported their time but now I've noticed that
some resources are showing weird Units on the task like 2,213%.
Could someone comment on how this comes about and how to correct it?
Thanks,
Andy Novak
UNT