In a project with four resources from the Enterprise Resource Pool, all of
them dedicated to this project, all assigned to about 40-50 tasks, two of
them won't level at all, and the other two do just fine. This is whether I
level the entire project or selected resources, and regardless of the timing
(my usual is week by week). The only unique thing about the 2 that won't
level is that they are the ones most recently added to the Enterprise
Resource Pool. All tasks have priority <1000. Any ideas??